Data Centers in Cheyenne, Wyoming

Cheyenne, Wyoming has 9 tracked data centers in Laramie, representing roughly 1,508 MW of capacity. 3 operational, 5 under construction and 1 planned.

City
Cheyenne, Wyoming
County
Laramie
Total facilities
9
Operational
3
Under construction
5
Planned
1
Tracked capacity
1,508 MW
Operators
Google, Green House Data, Meta, Microsoft

Facilities

FacilityOperatorLocationStatusCapacity
Meta Cheyenne WYMetaCheyenne, WYUnder construction250 MW
Meta Cheyenne WYMetaCheyenne, WYUnder construction250 MW
Azure Cheyenne CampusMicrosoftCheyenne, WYUnder construction200 MW
Microsoft Cheyenne 2MicrosoftCheyenne, WYUnder construction200 MW
Microsoft Cheyenne 2MicrosoftCheyenne, WYUnder construction200 MW
Microsoft CheyenneMicrosoftCheyenne, WYOperational150 MW
Microsoft CheyenneMicrosoftCheyenne, WYOperational150 MW
Google Cheyenne WYGoogleCheyenne, WYPlanned100 MW
Green House Data CheyenneGreen House DataCheyenne, WYOperational8 MW