Switch Data Centers in the United States
Switch has 29 tracked data centers in the United States across 4 states, totalling roughly 4,600 MW.
- Operator
- Switch
- US facilities
- 29
- States served
- NV, MI, GA, TX
- Tracked capacity
- 4,600 MW
Facilities
| Facility | Operator | Location | Status | Capacity |
|---|---|---|---|---|
| Switch Las Vegas SuperNAP | Switch | Las Vegas, NV | Operational | 250 MW |
| Switch Tahoe Reno | Switch | Reno, NV | Operational | 130 MW |
| Switch Grand Rapids | Switch | Grand Rapids, MI | Operational | 100 MW |
| Switch Atlanta | Switch | Atlanta, GA | Operational | 80 MW |
| Switch CITADEL Campus | Switch | Las Vegas, NV | Under construction | 200 MW |
| Switch LAS VEGAS Core | Switch | Las Vegas, NV | Operational | 100 MW |
| Switch LAS VEGAS 9 | Switch | Las Vegas, NV | Operational | 150 MW |
| Switch LAS VEGAS 10 | Switch | Las Vegas, NV | Operational | 200 MW |
| Switch LAS VEGAS 11 | Switch | Las Vegas, NV | Under construction | 250 MW |
| Switch CITADEL Reno | Switch | Sparks, NV | Operational | 130 MW |
| Switch CITADEL 2 | Switch | Sparks, NV | Operational | 200 MW |
| Switch CITADEL 3 | Switch | Sparks, NV | Under construction | 300 MW |
| Switch PYRAMID Grand Rapids | Switch | Grand Rapids, MI | Operational | 60 MW |
| Switch PYRAMID 2 | Switch | Grand Rapids, MI | Operational | 100 MW |
| Switch KEEP Atlanta | Switch | Atlanta, GA | Operational | 130 MW |
| Switch KEEP 2 | Switch | Atlanta, GA | Under construction | 200 MW |
| Switch ROCK Austin | Switch | Austin, TX | Operational | 100 MW |
| Switch LAS VEGAS Core | Switch | Las Vegas, NV | Operational | 100 MW |
| Switch LAS VEGAS 9 | Switch | Las Vegas, NV | Operational | 150 MW |
| Switch LAS VEGAS 10 | Switch | Las Vegas, NV | Operational | 200 MW |
| Switch LAS VEGAS 11 | Switch | Las Vegas, NV | Under construction | 250 MW |
| Switch CITADEL Reno | Switch | Sparks, NV | Operational | 130 MW |
| Switch CITADEL 2 | Switch | Sparks, NV | Operational | 200 MW |
| Switch CITADEL 3 | Switch | Sparks, NV | Under construction | 300 MW |
| Switch PYRAMID Grand Rapids | Switch | Grand Rapids, MI | Operational | 60 MW |
| Switch PYRAMID 2 | Switch | Grand Rapids, MI | Operational | 100 MW |
| Switch KEEP Atlanta | Switch | Atlanta, GA | Operational | 130 MW |
| Switch KEEP 2 | Switch | Atlanta, GA | Under construction | 200 MW |
| Switch ROCK Austin | Switch | Austin, TX | Operational | 100 MW |